2.1 In the last tariff order the
Commission had, while assessing the performance of the Board, had
set certain targets relating to various operational aspects of the
Board. The Commission has taken stock of the performance of the
Board in general and with respect to the targets set in the earlier
tariff order, in particular. Observations of the Commission in this
regard are discussed in the following paragraphs.
Category-wise Consumption
The comparison of actual category-wise
consumption with ARR filing projections and Commission�s approval
has been summarized below:
Category |
Actual Sales MU 2000-01
|
Actual Sales MU 2001-02
|
Difference |
LT
Consumers |
|
|
|
Domestic
|
2444.92 |
3070.27 |
25.58% |
Single Light
Point consumers |
239.82 |
132.28 |
-44.84% |
Non-domestic
|
578.15 |
604.39 |
4.54% |
Water Works
|
151.52 |
158.32 |
4.49% |
Industrial
|
628.38 |
676.97 |
7.73% |
Agricultural
|
3559.52 |
3726.52 |
4.69% |
Street
Lights |
126.82 |
127.19 |
0.29% |
TOTAL (LT)
|
7729.13 |
8495.94 |
9.92% |
HT Consumers
|
|
|
|
Railway
Traction |
1049.32 |
1142.55 |
8.88% |
Coal Mines
|
494.27 |
519.82 |
5.17% |
Mini Steel
Plants |
60.39 |
92.4 |
53.01% |
Cement
Factories |
507.84 |
530.18 |
4.40% |
HT
Irrigation |
14.26 |
9.88 |
-30.72% |
HT Water
Works |
288.67 |
294.57 |
2.04% |
Other HT
consumers |
2050.69 |
2353.57 |
14.77% |
RE
Co.Society |
832.21 |
171.23 |
-79.42% |
Border
Villages |
18.19 |
16.69 |
-8.25% |
TOTAL (HT)
|
5315.84 |
5130.89 |
-3.48% |
TOTAL LT +
HT |
13044.97 |
13626.83 |
4.46% |
An analysis of the above table indicates that the consumption by HT
categories is increasing at a lower rate as compared to consumption
by LT categories.
2.3 Category-wise Consumers
The comparison of number of consumers during last 3 years is given
below:
Categories |
1999-00 |
2000-01 |
2001-02 |
% Increase
over
1999-00 |
L T CONSUMERS
|
|
|
|
|
Domestic
|
2,714,504 |
3,227,184 |
4,036,232 |
48.69% |
Single Light
Point Consumers |
1,782,605 |
1,098,169 |
551,145 |
-69.08% |
Non-domestic
|
504,994 |
533,355 |
555,376 |
9.98% |
Water Works
|
11,192 |
12,416 |
13,589 |
21.42% |
Industrial
|
81,485 |
83,477 |
88,274 |
8.33% |
Agricultural
|
1,171,804 |
1,145,300 |
1,219,175 |
4.04% |
Street Lights
|
16,485 |
16,291 |
17,029 |
3.30% |
TOTAL (LT)
|
6,283,069 |
6,116,192 |
6,480,819 |
3.15% |
H T CONSUMERS
|
|
|
|
|
Railway
Traction |
33 |
32 |
32 |
-3.03% |
Coal Mines
|
35 |
36 |
39 |
11.43% |
Mini Steel
Plants |
16 |
14 |
15 |
-6.25% |
Cement
Factories |
21 |
21 |
23 |
9.52% |
HT Irrigation
|
60 |
58 |
58 |
-3.33% |
HT Water Works
|
91 |
89 |
88 |
-3.30% |
Other HT
consumers |
1278 |
1341 |
1362 |
6.57% |
RE
Co-operative Society |
14 |
14 |
4 |
-71.43% |
Border
Villages |
7 |
7 |
7 |
0.00% |
TOTAL (HT)
|
1555 |
1612 |
1626 |
4.57% |
TOTAL LT + HT
|
6284624 |
6117804 |
6482445 |
3.15% |
It is observed that overall increase
in the number of consumers in Board�s network has been around 3.15%.
While the increase in LT category has been around 3.15%, increase in
HT has been around 4.57%.
2.4 T&D losses
The reduction of T&D losses is a
major concern as approximately 50% of the energy is lost in transit.
This may either be pilferage and theft or on account of technical
losses. Reduction of losses to reasonable level not only results
into saving of valuable and costly resources of the MPSEB but also
ensures additional availability of power for consumers. T&D losses
during the past two years as assessed by MPERC in the last tariff
order and actual are given in the following table:
Years |
MPSEB |
MPERC |
Actual |
2001-02 |
42.88 |
42.88 |
48.77 |
The Board had mentioned that it would
be able to bring down the loss level to 42.88% during 2001-02, which
was accepted by the Commission. This meant reduction of 8.12
percentage points. However the actual reduction has been only 2.23
percentage points.
The Board has explained that in order
to have proper assessment of energy consumed by the agricultural
consumers, an exercise/sample survey covering 1278 agricultural
consumers situated at different geographically locations of Madhya
Pradesh has been conducted. The survey covered different crops
cultivated, in various divisions, circles, region, having proper
representation of all areas, all type of crops and all type of
sources of watering. Region-wise average consumption per HP/month
is as under:
S.No. |
Region |
Units/HP/Month |
1 |
Jabalpur |
72 |
2 |
Sagar |
83 |
3 |
Indore |
117 |
4 |
Bhopal |
98 |
5 |
Ujjain |
113 |
6 |
Rewa |
89 |
7 |
Gwalior |
78 |
Average |
98 |
The average consumption per HP/month
including all types of water sources, all type of crops and all
regions works out to 98 units. The aforesaid study covers a period
of about 4-5 months of the Rabi Season. Hence, the consumption for
five months of the Rabi Season may be considered as 98 units per
HP/month. Besides the Rabi Season, the consumption in other seasons
of the year is about 36% to 40% of the total consumption during the
year. Accordingly, for remaining seven months of the year, the
average consumption would be about 42 to 43 units per HP/month.
This will give average agricultural consumption of 65 to 66 units
per HP/month during the year 2001-02 which is equivalent to a load
factor of 12% as against 15% allowed by the Commission for the year
2001-02. With this load factor and the consumption of 20 units per
month per connection for SC/ST Single Light Point Connections for
2001-2002 and for other SLP connections at 20 units per month per
connection for the period April 2001 to September, 2001, and 60
units per month per connection for the period October 2001 to March
2002, The T&D losses for the year 2001-02 works out to 48.77% which
is nearly 49%. This tallies with the findings of losses of 49% in
the State based on the actual readings of the meters installed at
various sub-stations and feeders in various Divisions, Circles and
Regions for energy auditing work.
The figures of 12% load factor for
agricultural consumers and T&D losses of 49% are based on the actual
study conducted by installing meters at the premises of about 1278
consumers and the readings from meters at various sub-stations and
feeders. Once 100% metering is achieved, accurate agricultural
consumption or SLP consumption and accurate loss figures will be
computed. At present, aforesaid figures are purely based on the
limited study and these are subject to change. The load factor of
agricultural consumers or the T&D loss may be somewhat different in
future when full details would be available.
While passing the tariff order for the
year 2001-02, the Commission had directed that the T&D losses as
prevailing at the end of 2000-01, which was determined at 51%, shall
be reduced to 42.88% by 2001-02. Further, the Commission had
prescribed the following programme for reduction of T&D losses over
next five years:
Year |
Total Loss (%) |
Reduction (%) |
2000-01 |
51% |
- |
2001-02 |
42.88 |
8.12 |
2002-03 |
37.00 |
5.88 |
2003-04 |
32.00 |
5.00 |
2004-05 |
28.00 |
4.00 |
2005-06 |
25.00 |
3.00 |
The Board has explained that during
the year 2001-02, technical losses could not be reduced as it
requires huge investment for renovation of HT/LT transmission and
distribution system. Even if sufficient investments are tied-up, it
would take considerable time to reduce such losses. Under reforms
and restructuring process, the Asian Development Bank is providing
funding for renovation of the transmission and distribution system
in a phased manner for which action has been initiated.
Actual T&D losses for the year 2000-01
have been 50.97% as against 51% determined by the Commission. For
the year 2001-02, the estimated losses are 47.29% i.e. a reduction
of 3.7 percentage points. However, 10 nos. RE Societies have
recently been merged with the Board in the month of March, 2002 and
the losses being comparatively on higher side in REC Societies, the
T&D losses at the end of the year 2001-02 are estimated at 48.77%.
2.4.2 Steps for reducing high
Commercial Loss
For reducing high commercial loss,
which is of the order of 27%, the following steps need to be
initiated.
(i) Intensive checking of Jhuggi
Jhopadi clusters, agriculture sector and unauthorized colony.
(ii) Meter must necessarily be
installed at existing unmetered SLP and agriculture connections
within the given time frame of 3 years.
(iii) Close monitoring of HT/LT
industry to curb pilferage and misuse and that recorded
consumption is commensurate with actual use.
(iv) Precision Electronic Meters be
ensured on all HT consumers� premises and LT industries so that
theft of energy can be readily checked. No HT connection should
remain defective for a duration exceeding 7 days and similar action
for LT industries.
(v) Defective meters should be
replaced by making monthly programme and should be ensured that the
defective meters remain within the level of 2.5% i.e. 3% in the
rural areas and 1.5% within the township and urban area.
(vi) 100% meter reading of LT
consumers should be ensured. Supervisory officers (JE/AE) must be
given programme to exercise checks of 5% and 10% to ensure correct
recording to ensure correctness of meter reading.
2.4.3 Revised Schedule For Reduction Of T&D Losses
In the tariff order for the year
2001-02 approved by the Commission certain level of improvement in
T&D losses was approved against which the MPSEB came out with a
different programme. The MPSEB has worked out and projected
monthwise circle wise programme for reduction of losses from July,
2002 to November, 2003. 13 circles out of 35 circles of the MPSEB
has recorded very high level of T&D losses.
From the data presented by the MPSEB,
the Tikamgarh Circle has recorded as high as 63.93 % T&D losses
followed by 62.49 % in respect of Gwalior City Circle, 61.5% in
respect of Rajgarh Circle and 60.36% in respect of Shivpur Circle.
The analysis further indicates that only around 36% to 39% of the
power injected in to the system is available for sale.
The MPSEB has been continuously arguing
that high technical losses are because the required level of
investment is not possible. The figures projected by the Board do
not support the statement of the MPSEB for city circles controlling
corporation areas, such as Gwalior (CC), Bhopal (CC) and Indore (CC)
where infrastructure is relatively very good and has recorded more
or less the same level of losses.
Reduction of losses as suggested in the
programme of the Utility must be ensured. Accountability for
failure to achieve the set targets should be fixed and stringent
action should be initiated against employees concerned.
2.5 Energy Generation
2.5.1 Power Station- wise installed
capacity as on February 2002 is as follows:
Units
|
Capacity MW
|
|
A. THERMAL
POWER STATIONS |
i.
Amarkantak � I |
50
|
(1x30+1x20)
|
ii. Amarkantak � II |
240
|
(2x120)
|
Amarkantak
|
290
|
|
iii. Satpura � I |
187.50
|
(5x62.5) ---
60 % MP�s Share |
iv. Satpura � II |
410
|
(1x 200+1x210)
|
v. Satpura � III |
420
|
( 2x210)
|
Satpura
|
1017.50
|
|
vi. SGTPS � I |
420
|
(2x210)
|
vii. SGTPS � II |
420
|
(2x210)
|
SGTPS
|
840
|
|
TOTAL THERMAL
|
2147.50 |
|
B. HYDEL POWER
STATIONS : |
viii. Gandhi
Sagar |
57.50
|
( 5x23)
---50% MP�s Share |
ix. Bargi
|
90.00
|
(2x45)
|
x. Bansagar
Tons � I |
315.00
|
(3x105)
|
xi. Bansagar
Tons � III |
40.00
|
(2x20)
|
xii. Birsinghpur |
20.0
|
(1x20)
|
xiii. Rajghat
|
22.50
|
(3x15) -50%
MP�s Share |
xiv. Pench
Totladoh |
107.00
|
(2x80)
-66.67% MP�s Share |
xv.
Ranapratap Sagar (Operated by RSEB) |
86.00
|
( 4x43)- 50%
MP�s share |
xvi. Jawahar
Sagar (Operated by RSEB) |
49.50
|
(3x33) 50%
MP�s share |
xvii.
Matatila (Operated by UPSEB) |
10.00
|
(1x30) - 33%
MP�s share |
TOTAL HYDEL
|
797.50
|
|
C. Mini Micro
Hydel |
5.45
|
|
Grand Total
(A+B+C) |
2950.45
|
|
In the inter-state project viz. Satpura
Thermal Power Station No. 1 at Sarni, MPSEB has a share of 60%,
while Rajasthan owns the balance. In respect of Hydel Station viz.
Gandhi Sagar (Located in Madhya Pradesh having a capacity of 115
MW), Rana Pratap Sagar (located in Rajasthan having a capacity of
172 MW) and Jawahar Sagar (located in Rajasthan having a capacity of
99 MW), both the states own 50% share each. Also the MPSEB and the
MSEB (of Maharastra) have an inter state Hydel Power station namely
Pench Totladoh with a capacity of 160 MW wherein the MPSEB owns a
share of 66.67 % i..e 107, MW and 33.33% (53 MW) is owned by MSEB.
Apart from inter state power stations
with the states of Rajasthan and Maharastra, Madhya Pradesh also has
inter state projects with U.P. In Rajghat which has a capacity of 45
MW, both the state of Madhya Pradesh and UP share 50% each of the
power generated from this power station. Further, in Matatila hydel
station, which has a capacity of 30 MW, Madhya Pradesh has a share
of 33% (10 MW).
In addition to above, the MPSEB has a
share of 37.5 MW from Rihand (UP) and 5 MW from Hirakud (Orissa).
This has not been accounted for because this power is not being
physically transferred and the matter is under dispute with
respective State Govts.
Overall performance of the thermal
power stations owned by the Board for the years 1999-2000, 2000-2001
and 2001-2002 have been indicated below alongwith the performance
parameters fixed by the Commission for the year 2001-2002, for the
purpose of evaluation:
2.5.2 Plant Load Factor
Name of the
Power Station |
1999-2000 (actuals)
|
2000-2001 (actuals)
|
2001-02
|
MPERC
|
Actuals
|
Amarkantak
T.P.S. |
50.90%
|
45.3%
|
45.5%
|
38.99%
|
Satpura T.P.S.
|
76.9%
|
72.0%
|
76.2%
|
73.10%
|
SGTPS
Birsinghpur |
70.0%
|
66.8%
|
73.0%
|
57.28%
|
All Thermal
|
70.8%
|
66.7%
|
71.1%
|
62.90%
|
2.5.3 Auxiliary Power
Consumption
Amarkantak
T.P.S. |
10.43%
|
10.36%
|
10.0%
|
11.33%
|
Satpura T.P.S.
|
8.77%
|
8.93%
|
8.8%
|
8.88%
|
SGTPS
Birsinghpur |
10.52%
|
10.22%
|
9.0%
|
11.07%
|
All Thermal
|
9.43%
|
9.5%
|
9.0%
|
9.77%
|
2.5.4 Specific Oil
Consumption (ml/KWhr)
Amarkantak
T.P.S. |
3.56
|
7.318
|
- |
14.067
|
Satpura T.P.S.
|
1.63
|
2.07
|
- |
3.14
|
SGTPS
Birsinghpur |
2.48
|
4.9
|
- |
4.80
|
All Thermal
|
2.16
|
3.79
|
2.94
|
4.56
|
2.5.5 Station Heat Rate (kCal/ kWhr)
Amarkantak
T.P.S. |
2896
|
3330
|
2869
|
3572
|
Satpura T.P.S.
|
2698
|
2870
|
2689
|
3035
|
SGTPS
Birsinghpur |
4347
|
3120
|
2689
|
3195
|
All Thermal
|
3317
|
3002
|
2704
|
3137
|
It is evident from the above data that
the performance of the above thermal power stations has deteriorated
during the past three years and the PUF during the year 2001-02
declined to 62.9% against the target of 71.1% fixed by the
Commission. Similarly, the parameters for auxiliary power
consumption, fuel oil consumption and station heat rate achieved,
have not been comparable.
2.5.6 Reasons for the lower
performance are attributed mainly to the following:
i. Lack of timely maintenance of
the units owing to pressing demand for the power in the state.
ii. Unforeseen outages resulting from ageing.
iii. Non-availability of spares in adequate quantity.
iv. Lack of funds resulting in the deferment of
refurbishment/renovation/modernization activities of the units.
v. Non�supply of adequate quantity and quality of coal as per
the linkage decided by the Standing Linkage Committee.
Reasons for poor performance of each
station are discussed in following paragraphs.
AMARKANTAK THERMAL POWER STATION
(Capacity: 1x30+1x20+2x120= 290 MW)
i) The 2x30 MW units
of this power station (out of which one has already been derated to
20 MW capacity) were commissioned during 1965 and are as old as 36
years. Though the Board is striving to take up the refurbishment
works, they are yet to be awarded. Further, there has been a problem
of non-availability of coal mills spares resulting in the operation
of only one unit at a time.
ii) The 2x120 MW units were commissioned during
1977-78. The units are not working satisfactorily in as much as they
do not generate beyond 90 MW capacity each. Their R & M works have
got held up owing to the backing out of M/s Ensaldo Energia of Italy
who were awarded this work. Therefore, the performance of these
units could not be achieved to the desired level during the year
2001-02 as was envisaged.
In view of the above, the performance of Amarkantak TPS has been
continuously poor. Against the target of 45.5% for Amarkantak
complex as a whole, fixed by the Commission for the year 2001-2002
it achieved only 39%.
iii) Specific oil consumption for smaller units nos.
1 and 2 has been 14.067 ml/unit, which is abnormally high. The Board
is directed to investigate into the causes of this high level of
consumption for the year 2001-02 and take remedial steps.
SATPURA THERMAL POWER STATION:
(Capacity:5x62.5+1x200+1x210+2x210=1142.5 MW)
i) Units of PH- I
(5x62.5 MW) are as old as 32 to 35 years. During the year, units
no. 3 and 4 had to undergo major repairs of their turbine blades
and rotors. This repair took 77 days for each of the units.
ii) Due to scanty
rainfall during the year 2000, the Satpura lake did not contain
sufficient water and as a consequence there was a sharp decline in
the water level from April 2001 to June 2001. Generation, therefore,
had to be restricted resulting into a lower PUF.
iii) There was
unforeseen failure of LP turbine blades of 210 MW of unit no. 9 in
the month of February 2001. LP turbine rotor was dismantled and sent
to the BHEL Bhopal works for repair. Thereafter cracks were also
found in IP turbine rotor. After repair the rotors were received and
commissioned during July 2001. This resulted in lower PUF.
iv) Coal received for
PH- II and PH- III has comparatively lower CV than the designed
ones. Also coal received has an ash content of 40% or more against
the designed value of 28%.
In view of the above, the Board could
not achieve PUF target determined by the Commission for 2001-02.
SANJAY GANDHI THERMAL POWER STATION
BRISINGHPUR
(Capacity:2x210+2x210=840 MW)
The poor performance is due to
condenser tube problems associated with unit nos. 1 and 2 (2x210
MW), which were commissioned during the year 1993/1994, i.e. only
8/9 years ago, they are not functioning as desired. During the year
2001-2002, aluminum - brass tubes in their condensers, which had
prematurely failed, were completely replaced with the new copper-
nickel condenser tubes. Further coal shortage at the power station
also results in the generation loss.
In view of the above the SGTPS could
not achieve the PUF as determined by the Commission for 2001-02.
2.6 State
Government Subsidy
During the meeting, the Commission had
with the State Govt. on this issue last year, the State Government
had informed that for the year 2001-02, budget provision of
Rs.315.27 crore towards payment of subsidy to the Board has been
made. This includes payment of free supply to eligible agriculture /
SLP connections and tariff subsidy to agriculture consumers. The
Commission had sought a meeting with the State Government on
3.8.2001 on the quantum of Government subsidy required. The State
Government further informed that apart from the above budgeted
subsidy of Rs.315.27 crore, the Board can retain the electricity
duty collected (estimated at Rs.245 crore), which shall be treated
as additional subsidy for the year 2001-02. The Board received an
actual subsidy of Rs. 132 crore, which was Rs. 428 crore less than
agreed sum. This clearly affects the financial position of the Board
in a negative manner and ultimately in a lower quality of supply and
service to the consumer.
2.7 Revenue Requirement
MPSEB has submitted the details of the
actual expenditure incurred in FY02, under each head of expenditure
as given below:
FY02 ARR (in Rs. Crores)
S. No. |
Particulars |
Filed by MPSEB |
MPERC |
Revised Estimate |
Difference between 4 and 5
|
1 |
2 |
3 |
4 |
5 |
6 |
1 |
Own Generation Expenses
|
1240.13 |
1031.25 |
1061.74 |
-30.49 |
2 |
� Power
Purchase expenses |
2297.1 |
2297.1 |
2354.92 |
-57.82 |
|
�
Wheeling Charges of PGCIL and GRIDCO |
196.94 |
196.94 |
202.96 |
-6.02 |
3 |
Employees Expenses |
836.82 |
822.28 |
715.65 |
106.63 |
4 |
Administrative & General Expenses
|
92.99 |
66.67 |
65.93 |
0.74 |
5 |
Repair & Maintenance Expenses
|
|
|
|
|
|
(i) Generation |
197.99
|
197.99
|
109.3 |
77.95 |
|
(ii) T&D |
166.64 |
6 |
Depreciation |
595.96 |
440.79 |
497.65 |
-56.86 |
7 |
Interest, Finance Charges & lease
rentals |
686.9 |
585.05 |
851.38 |
-266.33 |
|
Less capitalized |
161.15 |
161.15 |
0 |
161.15 |
|
Net interest & finance charges
|
525.75 |
423.9 |
851.38 |
427.48 |
8 |
Bad debts |
163.87 |
74.01 |
237.87 |
-163.86 |
9 |
Other expenses |
24.61 |
0 |
0 |
0 |
10 |
Taxes on Income & Profit
|
|
0 |
0 |
0 |
|
Total (1 to 11) |
6173.65 |
5550.93 |
6264.04 |
-713.11 |
11 |
(a) Net fixed assets
|
4447.73 |
4581.32 |
4931.86 |
-350.54 |
|
(b) Less Consumers� Contribution
|
0 |
262.57 |
601.18 |
-338.61 |
|
( c) capital bases at the start of
the year |
4447.73 |
4318.75 |
4330.68 |
-11.93 |
|
( d ) 3% ROR |
133.43 |
129.56 |
129.92 |
-0.36 |
12 |
Total (1 to 12 ( c ) |
6307.08 |
5680.49 |
6393.96 |
-713.47 |
13 |
Less other non-tariff income
|
377.34 |
359.74 |
366.54 |
-6.80 |
15 |
Total revenue requirement (13-14)
|
5929.74 |
5320.75 |
6027.42 |
-706.67 |
Differences in various heads are
discussed in the following paragraphs.
2.8 Power Purchase
The Board had envisaged purchase of
13181.42 million units at a cost of Rs. 2513.64 crore at an average
cost of 190.70 paise per unit. The Commission had accepted this
projection. The actual purchase was 13746.61 million units at an
average rate of 186.07 paise per unit. There has been additional
purchase to the extent of 565.19 million units. This resulted into
an increase of Rs 57.82 crore as compared to the approved
expenditure.
2.9 Employees Cost
Actual expenditure has been lower by Rs.
106 crore primarily due to freezing of DA rates by the State
Government. Major heads of deviation are given below:
Particulars |
MPSEB
|
MPERC
|
Revised Estimate |
Difference between 3 and 4
|
1 |
2 |
3 |
4 |
5 |
Dearness Allowance |
232.69 |
218.15 |
165.92 |
42.17 |
Contribution to Pension Fund
|
85.62 |
85.62 |
51.06 |
26.56 |
Contribution to Gratuity Fund
|
25.48 |
25.48 |
16.60 |
8.88 |
2.10 Interest and Finance
Charges
The Board had proposed for expenditure
of Rs. 686.90 crore which was revised to 585.05 crore by the
Commission. However, the actual liability of the Board in this
regard was Rs. 1089.08 crore. This resulted into an increase of Rs.
504.02 crore over the amount approved by the Commission. Some of the
important differences are summarized below:
Rs. In crore
Particulars |
MPSEB
|
MPERC
|
Revised Estimate |
Difference between 3 and 4
|
1 |
2 |
3 |
4 |
5 |
Debentures |
77.42 |
32.37 |
77.42 |
45.05 |
IDBI |
23.31 |
13.35 |
26.12 |
12.77 |
Penal Interest Charges |
0 |
0 |
77.47 |
77.47 |
Penal Charges for delayed payment
for power purchases |
0 |
0 |
323.16 |
323.16 |
Interest to Provident Fund
|
0 |
0 |
14.50 |
14.50 |
Total |
100.73 |
45.72 |
518.67 |
472.95 |
The above table indicates that the
result of the revenue mobilization programme of the Board was
significantly lower than estimated, resulting in defaults in
obligations. This in turn attracted penal charges from
lenders/suppliers. Such shortfall would restrict the capability of
the Board to invest in new schemes and also maintenance of the
existing facilities. This is a matter of serious concern.
2.11 Depreciation
The Board had proposed depreciation of
Rs. 595.96 crore, which the Commission had restricted to Rs. 440.79
crore. The Board has submitted a revised estimate of Rs. 497.65
crore. In the absence of availability of reliable of records it is
difficult to pinpoint the reasons for such deviation.
2.12 Collection Efficiency
The Commission had directed the Board
to increase its collection efficiency to 96% during 2001-02. The
Board submitted that the same was improved to 92%. However, the
collection efficiency needs to be evaluated keeping in view the
total outstanding amount i.e. including previous years� arrears
also. The same is summarized as under:
|
2001-02 |
Net Receivables at the start of
year |
1773.94 |
Sales |
3706.87 |
Receivables at the end of year
|
1560.97 |
Collection |
3919.84 |
Average % Collection |
71.52% |
One of the major factors contributing
towards higher collections level was the payment of Rs. 200 crore of
dues by the Indore Municipal Corporation.
The Commission is of the opinion that
there is substantial scope for improving the collection efficiency.
Outstanding position as on 31.3.2002 represents 154 days� sales
equivalent. The Board should make concerted efforts to bring it down
to not more than 75 days� level. Needless to say, better collection
efficiency would enable the Board to borrow less and at better
terms.
2.13 Metering
The financial health of any utility is
critically dependent on an accurate assessment of revenue due and
its subsequent realization. MPSEB is not in the position to recover
the cost of supply through existing tariff. Thus, every additional
unit sold by MPSEB to the subsidized set of consumers adds to its
losses. In such a scenario, proper metering and energy audit are
important steps towards narrowing the gap. The Commission once again
stresses the need for 100% of metering at an early date.
In Madhya Pradesh there are 1639 HT
consumers. For all these HT consumers metering was completed by the
Board on 31/12/2001. The progress of installation and replacement of
stopped/defective meter on the LT side is, however, poor in some
areas. The current level of metering of LT consumers is indicated
below.
S.No |
Name of Circle |
Current level of metering in L.T.
in % |
1 |
Jabalpur city |
98.69 |
2 |
Jabalpur (O&M) |
68.15 |
3 |
Mandla |
68.94 |
4 |
Narsingpur |
64.37 |
5 |
Seoni |
72.90 |
6 |
Chhindwara |
38.59 |
7 |
Sagar |
58.51 |
8 |
Chhatarpur |
61.91 |
9 |
Tikamgarh |
53.15 |
10 |
Rewa |
65.03 |
11 |
Satna |
67.53 |
12 |
Sidhi |
45.35 |
13 |
Shadol |
46.10 |
14 |
Bhopal City |
87.69 |
15 |
Bhopal (O&M) |
56.86 |
16 |
Sehore |
54.08 |
17 |
Rajgarh |
55.14 |
18 |
Hoshangabad |
65.56 |
19 |
Betul |
77.92 |
20 |
Gwalior City |
94.31 |
21 |
Gwalior (O&M) |
59.92 |
22 |
Morena |
74.19 |
23 |
Guna |
76.45 |
24 |
Shivpuri |
56.18 |
25 |
Indore City |
99.02 |
26 |
Indore (O&M) |
63.13 |
27 |
Khandwa |
56.88 |
28 |
Khargone |
47.61 |
29 |
Dhar |
26.04 |
30 |
Jhabua |
32.20 |
31 |
Ujjain |
69.36 |
32 |
Dewas |
59.53 |
33 |
Shajapur |
51.98 |
34 |
Ratlam |
57.03 |
35 |
Mandsour |
54.97 |
It is observed that in some circles
such as Chhindwara, Sidhi, Khargone and Jhabua the level of metering
is below 50%. The progress towards replacement of stopped/defective
meters, particularly for LT consumers in some of the regions, is
also unsatisfactory. Against a total of 42,50,139 installed LT
meters, the percentage of stopped/defective meters as on 31.03.2002
was 8.81%. The maximum percentage of stopped/defective meters is
12.89% in Gwalior region. The region-wise percentage of
stopped/defective meters and progress of replacement is indicated
below.
REPLACEMENT OF DEFECTIVE METERS
|
S. No. |
Name Of Circles And Regions
|
No Of LT Meters Installed
|
No. Of Stopped/ Defective Meters at
the beginning of 2002-03 |
% Stopped /Defective Meters To
Total No. Of Installation at the beginning of 2002-03
|
Balance No. Of Stopped / Defective
Meters at the end of Aug'2002 |
% Of Stopped/Defective Meters To
Total No. Of Installation at the end of Aug'2002 |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
Jabalpur |
806333 |
45083 |
5.59 |
31762 |
4.00 |
2 |
Sagar |
341758 |
37628 |
11.01 |
20479 |
6.07 |
3 |
Rewa |
356939 |
9436 |
2.64 |
9683 |
2.76 |
4 |
Bhopal |
643371 |
69529 |
10.81 |
40068 |
6.36 |
5 |
Gwalior |
555467 |
108770 |
19.58 |
70473 |
12.89 |
6 |
Indore |
826421 |
49794 |
6.02 |
29025 |
3.70 |
7 |
Ujjain |
719850 |
54242 |
7.53 |
28369 |
3.94 |
|
TOTAL: |
4250139 |
374482 |
8.81 |
229859 |
5.52 |
2.14 Audit Report (Commercial)
for the year ending 31st March, 2002
Audit of MPSEB was conducted from
December, 2000 to June, 2001 covering records of Chief Engineer
(Generation) & Chief Engineer (T&D) at Head Office and 9 Areas and
10 Generation Stores for the last 5 years for the year ending March,
2002. The main findings of the audit report on the test check of
the records indicate that the Board had not laid down effective
inventories, control measures by stipulating the minimum, maximum,
reordering and critical level of stores. There was no system to (a)
properly assess requirement before purchase; (b) for replacing the
defective materials; (c) periodical identified surplus materials and
dispose them expeditiously.
The Board should immediately
introduce system to accurately assess system before making purchase
and also identify surplus material and dispose them of
expeditiously. |