50/2021 |
In the matter of petition under section 86(1)(f) of the Electricity Act,2003 read with Regulation 10 of the MPERC (Cogeneration and Generation of Electricity from Renewable Sources of Energy) Regulations, 2020 (Revision I) and Retail Supply Tariff Order for FY
2020-21, seeking adjudication on the issue of applicability of HV-7 Tariff on power consumed for synchronization of power for generators connected to the grid. |
1) M/s Arya Energy Limited, Raipur 2) MP Biomass Energy Developers Association, Bhopal |
1) MP Poorva Kshetra Vidyut Vitran Company Limited |