| Sr No | Petition No/year | Petitioners | Respondents | Subject | Section | Last Hearing Date | Attachments |
|---|---|---|---|---|---|---|---|
| 1 |
122/2025 [Licensing & Regulation ] |
1) M/s Arya Energy Limited, Raipur |
1) Managing Director, MP Power Management Company Limited |
Petition under section 86(1)(B), Section 86(1)(E), Section 86(1) (F), Section 86(1)(K) and 86(4) of the Electricity Act, 2003 for adjudication of dispute with Madhya Pradesh Power Management Co. Ltd. | Section 86 of the Electricity Act, 2003 | 14-07-2026 |
View
Daily
Orders
|
| 2 |
144/2025 [Licensing & Regulation ] |
1) M/s Continuum MP Windfarm Development Pvt. Ltd. Jaora, Ratlam, (MP) |
1) MP Poorva Kshetra Vidyut Vitran Company Limited 2) MP Madhya Khsetra Vidyut Vitran Compnay Limited 3) MP Pashchim Kshetra Vidyut Vitran Company Limited 4) SLDC State Load Dispatch Center 5) Managing Director, MP Power Management Company Limited |
Petition under sections 86(1) (F) of the Electricity Act, 2003 read with Regulation 45 and Regulation 47 of the MPERC (Conduct of Business) Regulations 2016. | Regulation-45 of MPERC (Conduct of Business),Section 86 of the Electricity Act, 2003 | 14-07-2026 |
View
Daily
Orders
|
| 3 |
145/2025 [Licensing & Regulation ] |
1) M/s Continuum MP Windfarm Development Pvt. Ltd. Jaora, Ratlam, (MP) |
1) MP Poorva Kshetra Vidyut Vitran Company Limited 2) MP Madhya Khsetra Vidyut Vitran Compnay Limited 3) MP Pashchim Kshetra Vidyut Vitran Company Limited 4) SLDC State Load Dispatch Center 5) Managing Director, MP Power Management Company Limited |
Petition under sections 142 of the Electricity Act, 2003 for compliance of the order dated 18.08.2025 passed by this Hon\'ble Commission in Petition No. 29 of 2025 and I.A. No. 21 & 23 of 2025. | Section 142 of the Electricity Act 2003 | 14-07-2026 |
View
Daily
Orders
|
Copyright © 2024 - MPERC.
Contents Provided, Updated & Maintained By
MPERC, Bhopal (M.P.)
Disclaimer : While every care has been taken to ensure the accuracy of information furnished in this website, MPERC does not accept any responsibility or liability for any damage or loss to any person for the result of any action taken on the basis of this information. However, MPERC shall be obliged if errors/omissions are brought to its notice for carrying out corrections in the next update.