6/2021 |
In the matter of petition under clause (b) of proviso 1 of Section 86 of the Electricity
Act 2003, seeking certain deviations from Model Power Purchase Agreement (PPA)
for procurement of power from decentralized Solar Power Plants having capacity of
five hundred (500) kW to two (2) MW to be set up under Component-A of Pradhan
Mantri Kisan Urja Suraksha evam Utthan Mahabhiyan Scheme (PM KUSUM) Scheme
introduced by Government of India (GoI) dated 22nd July 2019. |
1) M.P. Urja Vikas Nigam Limited 2) Managing Director, MP Power Management Company Limited |
|